(1) The installation position of the pneumatic control valve should be at a certain height from the ground, and a certain space should be left above and below the valve to facilitate disassembly and repair of the valve. For control valves equipped with pneumatic valve positioners and handwheels, operation, observation and adjustment must be convenient.
(2) The control valve should be installed on a horizontal pipeline and vertically above and below the pipeline. Generally, it should be supported under the valve to ensure stability and reliability. For special occasions, when the control valve needs to be installed horizontally on a vertical pipeline, the control valve should also be supported (except for small-diameter control valves). During installation, avoid adding additional stress to the control valve.
(3) The working environment temperature of the control valve should be between (-30 and + 60) and the relative humidity should not exceed 95%.
(4) There should be a straight pipe section before and after the control valve, and the length should not be less than 10 times the pipeline diameter (10D) to avoid the straight pipe section of the valve being too short and affecting the flow characteristics.
(5) When the diameter of the control valve is different from that of the process pipeline, a reducer should be used for connection. When installing a small-diameter control valve, a threaded connection can be used. The fluid direction arrow on the valve body should be consistent with the fluid direction.
(6) A bypass pipeline should be set up. The purpose is to facilitate switching or manual operation, and the control valve can be repaired without stopping the machine.
(7) Before installing the control valve, foreign matter in the pipeline, such as dirt, welding slag, etc., must be thoroughly removed.